Below you will find information that might help you understand how to find things or learn about information you might need to know about your city or town.
Inspection Information
15-
Inspection Information
Once a permit is issued for a job, an inspection can be scheduled by the contractor and/or owner via MyPermitNow.
-
Inspection Information
Inspections are conduction within 24 to 48 hours after the request is made on MyPermitNow or after the call is received on our inspection line.
-
Inspection Information
Applicants can view the inspection results online at MyPermitNow, or by email or phone call. The inspector will also leave a Building Inspection Report indicating approved, corrections required, correct and proceed, or failed. If the inspection failed, the Building Inspection Report will include the corrections to be made and a re-inspection if needed.
-
Inspection Information
There are no inspection fees, on re-inspection fees.
The re-inspection fee for a new residence is $35. Remodel fees for residential and commercial are $100 for each trip the inspector may make to the construction site.
-
Inspection Information
Building Electrical Plumbing Mechanical Miscellaneous Foundation Rough Rough Rough Pool Framing Finish Wiring Sewer Final Roof Insulation Service Water Driveway Wallboard Underground Top Out Chimney Final Temporary Gas Irrigation Final Final Backflow -
Inspection Information
When the water and sewer line(s) are installed along with a test performed prior to covering up, and prior to any electrical installed.
-
Inspection Information
Prior to the placement of concrete.
-
Inspection Information
After all above floor electrical, plumbing, and mechanical vents/ducts/unit(s) are installed and prior to placement of the insulation.
-
Inspection Information
Prior to wallboard installation, per the 2009 International Energy Conservation Code.
-
Inspection Information
Prior to tape and float/painting (includes Firewall Inspection if required).
-
Inspection Information
Prior to the placement of concrete.
-
Inspection Information
The Fire Marshal inspects the fire sprinklers, alarms, smoke control systems, and fire exits. The Fire Department will assess the type of construction, contents of the building, adequacy of fire protection equipment, and risks posed by adjoining buildings.
-
Inspection Information
Your facility will need to be inspected only if there is a "change of use" for the building.
For example, if a building was previously used as a retail shop and now it is a restaurant, the building needs to pass inspection by the Fire Marshal and Building Official to ensure the building meets the current building codes and city ordinance(s) and is safe for its new use. If a new tenant comes into the building and the use is the same or similar, no inspections need to be conducted. A certificate of occupancy will be issued to the new tenant.
-
Inspection Information
The final inspection is conducted after the building and site is finished and ready for occupancy.
-
Inspection Information
A Certificate of Occupancy is a document issued by the City of Marble Falls certifying a building's compliance with applicable building codes and city ordinances, and indicating it to be in a condition suitable for occupancy.